The PG&E panel upgrade process: steps and timeline in the East Bay
By Ally Electric & Solar, family-owned in Richmond since 2002
A panel upgrade involves three parties: your electrician, your city's building department and PG&E. Knowing the steps helps you plan the day the power goes off and avoid the delays that stretch some projects out.
Step 1: Load calculation
Your electrician totals what the home could draw at once, including planned additions like an EV charger or heat pump, and sizes the new service to match. Sometimes this shows a smart panel can avoid a service upgrade altogether.
Step 2: City permit
Replacing a panel or upgrading service requires an electrical permit from your city, or from Contra Costa County in unincorporated areas like Kensington. Your contractor pulls it.
Step 3: PG&E service application
When the service size or meter changes, your electrician files an application with PG&E. PG&E checks whether its own equipment, such as the service drop or transformer, can support the new service, and may send someone to look.
Overhead services are usually more straightforward. Underground services and meter relocations take more coordination.
Step 4: Installation day
PG&E disconnects the power, and the crew replaces the meter main or panel and brings grounding and bonding up to current code. Most homes are without power for one working day.
Step 5: Inspection and reconnection
The city inspector checks the work and signs off, and PG&E restores power to the new service. Your contractor coordinates both.
What slows upgrades down
Underground service, work on PG&E's transformer, moving the meter, incomplete applications and inspection backlogs are the usual causes. Sending your contractor clear photos of the meter and panel early, and deciding the panel location up front, keeps things moving.